View of side deckRick BJan 20, 2009
|
|

Rear and side view of houseRick BJan 20, 2009
|
|

The family chedi in the back yardRick BJan 20, 2009
|
|

View of driveway just pouredRick BJan 20, 2009
|
|

Random files - Rick B's Gallery |

View of front of perimeter wall and pedestrian gate before paintingRick B
|
|
|

Floor slabs (pan peun) are being laid for the first floor. These slabs will be covered with wire mesh and an additional 5cm of poured concrete.Rick B
|
|

Gypsum board installed and tapedRick B
|
|

Driving 7m long piles for the house footers. A total of 32 piles were driven for the house, which has a first floor foot print of 17.3m x 16.1m. Rick B
|
|

Pouring and smoothing concrete for the driveway in front of the house.Rick B
|
|

Inside kitchen after being tiledRick B
|
|

Alligning Window FrameWe used mai takien for our frames and windows. Here they're alligning one of the living room windows before cementing it in place.Rick B
|
|

|
|
|