Top rated - Cool Thai House Phase 2
IMG_1710.jpg
Formwork AssemblyThe metal forms are clipped into place using u bolts. They are rented at a daily rate depending with a price for each piece used. dozer00000
(0 votes)
IMG_1707.jpg
Metal FormworkThe metal formwork for the columns is lowered into place. The ordered quantity of forms was enough to allow the columns to be poured in two groups with one week allowed for curing. dozer00000
(0 votes)
IMG_1689.jpg
Spacers in WalkwayPreparing for the walk way pour around the exterior of the house. Although they are placing spacers they don't really work well for a floor pour as the rebar gets stepped on and bends. Here they are using 6mm rebar and wiring it together as opposed to the prefab welded rebar mesh. dozer00000
(0 votes)
IMG_1687.jpg
Rebar Level being SetThe prefab welded rebar mesh is adjusted into place during the floor pour. dozer00000
(0 votes)
IMG_1640.jpg
PatioThe patio was poured 5 cm lower than the normal floor. Note that the ground beam on the outside of the patio was lowered by 5 cm. dozer00000
(0 votes)
IMG_1630.jpg
FloorThe floor after the pour. The surface is rough broomed to prepare it for the tile. dozer00000
(0 votes)
IMG_1629.jpg
Rebar on top of PlasticThere is a piece of rebar which holds the welded rebar mesh in place until the floor is poured. It will be lifted into place during the floor pour (positioned half way in the floor). dozer00000
(0 votes)
IMG_1616.jpg
Floor LevelThe wood stakes indicate the level of the floor pour. The rebar being used is the prefab rebar mesh (that comes in a roll) type typically used in flooring. dozer00000
(0 votes)
IMG_1612.jpg
Damp CourseAnother view of the damp course plastic sheeting. dozer00000
(0 votes)
IMG_1607.jpg
Damp Course put in PlaceUsing a heavier plastic that doesn't tear easy like the saran wrap type ones normally used. This is designed to keep moisture from seeping into materials above it. In addition a waterproofing agent is used on the floor pour.dozer00000
(0 votes)
IMG_1600.jpg
Laser LevelChecking the layout with a laser level which shoots a beam straight ahead and also at a 90 degree angle as well as vertical. dozer00000
(0 votes)
IMG_1591.jpg
Soil CompactingUsing a rented vibrator to compact the soil. There are benzine and diesel models rated by weight. dozer00000
(0 votes)