Bathroom window framed. Notice the cement base below the window and the use of red brick above.dozerSep 27, 2011
|
|

Bathroom door being framed. This was a repair job. dozerSep 27, 2011
|
|

These window frames show the how a cement base is placed above and below the window frame, and how the red bricks are used to level out the wall above the window. (28-Mar-04)dozerSep 27, 2011
|
|

Starting to frame a bedroom door. A piece of 2 * 4 is used to keep the door in place.dozerSep 27, 2011
|
|

Front door of house framed. There is a cement base above the door frame. (22-Mar-04)dozerSep 27, 2011
|
|

Two windows framed. There is a 'leveled' cement base below the window frame and bricks are being used to level the wall to be even with the top of the frame. (13-Mar-04)dozerSep 27, 2011
|
|

Finished roof, view from rear.dozerSep 27, 2011
|
|

Finished roof, view from right front.dozerSep 27, 2011
|
|

Finished roof, view from right front.dozerSep 27, 2011
|
|

This is the final fix to the valley on the right side of the house. Added flashing material is being added. (30-Jun-04)dozerSep 27, 2011
|
|

For comparisons sake, a pair of photos of another house, which shows a wide strip of aluminum flashing (about 1 meter wide) being used which is a better way to do the roof flashing. (15-May-04/09-May-04)dozerSep 27, 2011
|
|

Patio roof section along in foreground. (10-May-04)dozerSep 27, 2011
|
|