Postby pipoz » Sat May 17, 2014 1:14 pm

Finally decided to start the process of a more permanent house.

Having started with a simply Bamboo House, whilst trying to buy the neighbours land, I gave up waiting for him to sell and decided to build in several stages, starting with a Studio-Guesthouse. I will just have to starve him out, over the next six months.

Pictures of my Bamboo house, which will serve as a shelter for the workers an eventually be demolished in 3 - 4 months’ time.

Attached is the "Happy House Concept", with a Studio Guesthouse at the Rear (sits just in from of the Bamboo house) and then the Main House in Front.

pipoz
Attachments
Bamboo House 2012.jpg
Bamboo House
Bamboo House 2013.jpg
Bamboo House
Happy House 001.pdf
HH Concept 001
(181.78 KiB) Downloaded 115 times
User avatar
pipoz
 
Posts: 1894
Joined: Mon Jan 23, 2012 10:41 pm
Location: Udon Thani Sometimes

Re: Udon Thani Happy House

Postby pipoz » Sat May 17, 2014 2:57 pm

Having decided to kick off with the Studio Guesthouse, next step was to choose a Façade concept and develop some drawings. Starting with the structure, I developed a set of structural drawings and added a few photos from CTH of what I wanted to achieve. (PS advanced thanks to other members for their kind photo donations)

Studio Guesthouse: Is 96 m2 Internal living area, with another 55 m2 for the Verandah are (External Paved area). Total Footprint is 151 m2 under Roof Line

Attached are some of the drawings for the set out-footings, foundation ground beams and slab, roof RC ring beam and external wall layout. If anyone is interested in them in AutoCAD or PAD I have them, but files are too large to upload on CTH.

Armed with some drawings of the Structure for the Studio-Guesthouse and a cost plan, I went to Udon Thani start of May and found a small builder through the local network. Sat with him end last week, agreed a price for the Structure only (as I am still developing the roof, façade and interior). Builder started on Saturday 10 May and said it would take him about 55 Days to complete the Structure/External walls. Fine with me.

pipoz
Attachments
Happy Studio-Guesthouse.jpg
Facade Concept for Studio Guesthouse
HH Facade Concept Part 1.pdf
Facade Concept
(102.13 KiB) Downloaded 265 times
HH Footing Layout Part 2.pdf
Set Out & Footings
(129.12 KiB) Downloaded 262 times
HH External Gound Beam B2 Part 3.pdf
External Pavement Ground Beam B2
(175.97 KiB) Downloaded 208 times
SHH Main House Ground Beam B1 Part 5.pdf
Main House Ground Beam B3
(137.12 KiB) Downloaded 198 times
HH Roof Beam B3 Part 6.pdf
Roof Ring Beam B3
(103.15 KiB) Downloaded 179 times
HH External Wall Block Work Layout Part 7.pdf
External Wall Layout
(136.48 KiB) Downloaded 199 times
User avatar
pipoz
 
Posts: 1894
Joined: Mon Jan 23, 2012 10:41 pm
Location: Udon Thani Sometimes

Re: Udon Thani Happy House

Postby pipoz » Sat May 17, 2014 3:22 pm

Off and running Day 1 to Day 5, move some of my established trees, set-out, excavate, pay Buddha and pour some footings.

I managed to have time to check his set out and some footing excavations before I left, and all was OK. Now have to leave it in her hands and now have to rely on photos from a distance, whilst I go back to work.

The two basic rules I gave him, are that the Reinforcement has to be SD 40 or 50, (No less) and Concrete has to be from CPAC 280 Steng.
Attachments
Day 1 Move a few Plants.JPG
Day 1 Move some Trees- Plants
Day 2 Start Set Out & Excavate.JPG
Day 2 Set Out and Excavate Footings
Day 3 Buddha.jpeg
Day 3 Traditional Buddha Offer
Day 5 Reo & Footings.jpeg
Day 5 Pour Footings
User avatar
pipoz
 
Posts: 1894
Joined: Mon Jan 23, 2012 10:41 pm
Location: Udon Thani Sometimes

Re: Udon Thani Happy House

Postby pipoz » Sat May 17, 2014 6:05 pm

Day 7 and back up to Ground Level.

Now have to do some work on the road and entrance (shift a electricity pole) for the bigger truck deliveries. Then Ground Beams should start mid this week.
Attachments
Day 7 Footing Column Necks Poured.jpg
Day 7 Footing Column Necks Poured
User avatar
pipoz
 
Posts: 1894
Joined: Mon Jan 23, 2012 10:41 pm
Location: Udon Thani Sometimes

Re: Udon Thani Happy House

Postby Ians » Sun May 18, 2014 9:29 am

Good luck with your build, looking forward to seeing it develop.
User avatar
Ians
 
Posts: 926
Joined: Thu Apr 24, 2008 11:38 am
Location: Phitsanulok

Re: Udon Thani Happy House

Postby Makmak456 » Sun May 18, 2014 7:16 pm

Off to a good start....
Mark
Makmak456
 
Posts: 575
Joined: Tue May 01, 2012 5:38 pm

Re: Udon Thani Happy House

Postby pipoz » Wed May 21, 2014 12:43 pm

Thanks

Slow but steady progress. Expect to pour on Day 14
Attachments
Day 10 Ground Beams Reo & Formwork 20 May 2014.jpeg
Day 10 Ground Beams
User avatar
pipoz
 
Posts: 1894
Joined: Mon Jan 23, 2012 10:41 pm
Location: Udon Thani Sometimes

Re: Udon Thani Happy House

Postby pipoz » Fri May 23, 2014 1:02 pm

Day 12, pouring half the ground beams
Attachments
Day 12 Pouring some of the Ground Beams 1 22 May 2014.jpeg
Day 12 Half Ground Beams
User avatar
pipoz
 
Posts: 1894
Joined: Mon Jan 23, 2012 10:41 pm
Location: Udon Thani Sometimes

Re: Udon Thani Happy House

Postby pipoz » Sat May 24, 2014 4:54 pm

Bought the largest one of these a few days back just to make, they (not her) use one, whilst I am not there.
Attachments
Vib Photo0498 (Small).jpg
Thaiwasatdu Conc Vibrator
User avatar
pipoz
 
Posts: 1894
Joined: Mon Jan 23, 2012 10:41 pm
Location: Udon Thani Sometimes

Re: Udon Thani Happy House

Postby pipoz » Fri May 30, 2014 8:23 pm

Day 16 Ground Slab down.

Got a few quality problems, with the Thai's having done what they want and not what I want.

Can be fixed, but they do piss you off sometimes when they do their own thing
Attachments
0-0  Ground Slab  Day 16.jpeg
Day 16 Ground Slab Poured
User avatar
pipoz
 
Posts: 1894
Joined: Mon Jan 23, 2012 10:41 pm
Location: Udon Thani Sometimes

Re: Udon Thani Happy House

Postby pipoz » Fri May 30, 2014 8:35 pm

Days 17 & 18

External Pavement Slab areas poured and Column Forms being erected

Should finish the structure (ring beam) in about 2 weeks
Attachments
Day 17 External Pavement Slabs Poured.jpeg
Day 17 External Pavement Slabs
0 Day 18 Column Forms Erected (Large).jpeg
Day 18 Column Forms
User avatar
pipoz
 
Posts: 1894
Joined: Mon Jan 23, 2012 10:41 pm
Location: Udon Thani Sometimes

Re: Udon Thani Happy House

Postby Roger Ramjet » Fri May 30, 2014 9:46 pm

pipoz wrote:External Pavement Slab areas poured and Column Forms being erected

I like the size of the columns, but make sure they brace them after they use the level to make sure they are square.
User avatar
Roger Ramjet
 
Posts: 5263
Joined: Tue Apr 27, 2010 12:55 pm

Re: Udon Thani Happy House

Postby pipoz » Sat May 31, 2014 11:59 am

Roger Ramjet wrote:
pipoz wrote:External Pavement Slab areas poured and Column Forms being erected

I like the size of the columns, but make sure they brace them after they use the level to make sure they are square.


Hi Roger and thanks.

They are 250 x 250 mm with 8* x DB 16 bars. They should be 3 meter high to underside of the RC Ring Beam, if the guy reads my drawings.

Also under certain areas of the line of the ring beam for a meter either side of some columns there will be load bearing reinforced/concrete fill block walls. That's the intention
Attachments
DRAWING-130.pdf
Roof Ring Beam Dwg 130
(249.96 KiB) Downloaded 155 times
User avatar
pipoz
 
Posts: 1894
Joined: Mon Jan 23, 2012 10:41 pm
Location: Udon Thani Sometimes

Re: Udon Thani Happy House

Postby pipoz » Tue Jun 03, 2014 7:56 pm

Day 20 31 Saturday May 2014

Sorry about the photos, but have to rely on others to take pictures
Attachments
00 Day 20 FWK Ring Beam 2.jpeg
FWK to Ring Beam Day 20
00 Day 20 FWK Ring Beam 1.jpeg
FWK to Ring Beam Day 20
User avatar
pipoz
 
Posts: 1894
Joined: Mon Jan 23, 2012 10:41 pm
Location: Udon Thani Sometimes

Re: Udon Thani Happy House

Postby pipoz » Sun Jun 08, 2014 9:26 pm

Day 24 view from the front

Like all things the Builder doesn't read the drawings, so I now have six extra columns at the front. The four in the center view, I will knock down.

Still better than leaving a column out.
Attachments
01 Day 24 Form Ring Beam Front West -  04 June 2014.jpeg
Front View West
02 Day 24 Form Ring Beam Front Center - 04 June 2014.jpeg
Front View Center
03 Day 24 Form Ring Beam Front East - 04 June 2014.jpeg
Front View East
User avatar
pipoz
 
Posts: 1894
Joined: Mon Jan 23, 2012 10:41 pm
Location: Udon Thani Sometimes

Next

Return to Your Building Story

Who is online

Users browsing this forum: No registered users and 1 guest

cron